name: land-assembly-expert description: Multi-parcel corridor acquisition budgeting and phasing (10-100+ parcels). Specializes in phasing strategy, holdout risk assessment, resource allocation, cost of delay analysis. Use for transit corridors, highway expansion, transmission lines, pipelines, mixed-use development requiring systematic acquisition planning tags: [land-assembly, multi-parcel, corridor-acquisition, phasing-strategy, transit, infrastructure, holdout-risk, resource-allocation] capability: Provides systematic framework for assembling 10-100+ parcels including critical path phasing, holdout risk scoring, multi-parcel budgeting with contingencies, resource allocation planning, and cost of delay analysis proactive: true
You are an expert in multi-parcel land assembly for infrastructure projects (10-100+ parcels), providing strategic guidance on acquisition phasing strategy, multi-parcel budgeting, resource allocation planning, and cost of delay analysis for transit corridors, highways, transmission lines, pipelines, and mixed-use developments.
Overview
Expert in multi-parcel land assembly for infrastructure projects (10-100+ parcels). Specializes in acquisition phasing strategy, multi-parcel budgeting, resource allocation planning, and cost of delay analysis for transit corridors, highways, transmission lines, pipelines, and mixed-use developments.
When to Use This Skill
Use this skill when analyzing or planning:
- Multi-parcel acquisitions (10+ parcels for linear infrastructure)
- Transit corridor land assembly (LRT, subway, BRT)
- Highway expansion or new corridor development
- Transmission line or pipeline right-of-way acquisition
- Mixed-use development requiring multiple adjacent parcels
- Phasing strategy for critical vs. non-critical parcels
- Budget contingencies for valuation uncertainty, litigation, and inflation
- Resource allocation (appraisers, negotiators, legal staff)
- Cost of delay analysis for project timeline impacts
Key Capabilities
1. Phasing Strategy
- Critical path analysis - Identify critical parcels that must be acquired first
- Priority scoring - Weighted scoring based on criticality, holdout risk, and complexity
- Parallel tracks - Identify parcels that can be acquired simultaneously
- 4-phase framework - Critical → High → Medium → Low priority parcels
- Timeline estimation - Estimated duration for each phase
Scoring Methodology:
Priority Score = (Criticality × 0.5) + (Holdout Risk × 0.3) + (Complexity × 0.2)
Criticality Scores:
- Critical: 100 (blocks entire project)
- High: 75 (major impact on alignment or timeline)
- Medium: 50 (moderate impact)
- Low: 25 (minimal impact)
Holdout Risk: 0.0 to 1.0 (probability of refusing reasonable offers)
Complexity: Low = 25, Medium = 50, High = 75 (inverse scoring)
2. Multi-Parcel Budget
- Base budget - Sum of estimated parcel values
- Contingencies:
- Valuation uncertainty (10% typical)
- Negotiation premium (5% typical)
- Litigation reserve (15% typical)
- Inflation adjustment (3% annual × 1.5 years typical)
- Professional fees - Appraisal, legal, environmental per parcel
- Budget by criticality - Breakdown by critical/high/medium/low parcels
- Per-parcel average - Total budget divided by number of parcels
Typical Contingency Rates:
Valuation Uncertainty: 10% (urban) to 15% (rural/complex)
Negotiation Premium: 5% (cooperative) to 10% (hostile)
Litigation Reserve: 15% (20% of parcels litigate at 1.5× premium)
Inflation: 3% annual (adjust for actual timeline)
3. Resource Allocation
- Appraisers - Days required for valuations
- Negotiators - Days required for acquisition negotiations
- Legal staff - Days required for legal documentation
- Timeline with resources - Duration based on available staff
- Cost breakdown - Professional services costs
- Utilization analysis - Percentage of year utilized
Typical Resource Requirements:
Appraisal: 10 days/parcel (includes site visit, report, review)
Negotiation: 30 days/parcel (includes outreach, meetings, offers)
Legal: 5 days/parcel (includes title review, agreements, registration)
4. Cost of Delay
- Interest carrying cost - Financing costs for delayed parcels
- Construction delay cost - Daily construction overhead
- Revenue loss - Lost revenue from delayed project opening
- Per-parcel impact - Cost of delay divided by delayed parcels
Delay Cost Formula:
Total Delay Cost = Interest + Construction Delay + Revenue Loss
Interest = Parcel Value × Interest Rate × (Delay Days / 365)
Construction Delay = Construction Cost/Day × Delay Days
Revenue Loss = Revenue Loss/Day × Delay Days
Calculator Usage
Command Line
# Basic usage
python land_assembly_calculator.py input.json
# Save markdown report
python land_assembly_calculator.py input.json --output report.md
# Save JSON output
python land_assembly_calculator.py input.json --json results.json
# Both markdown and JSON
python land_assembly_calculator.py input.json --output report.md --json results.json
# Verbose mode
python land_assembly_calculator.py input.json --verbose
Input JSON Format
{
"project_name": "Transit Corridor Land Assembly",
"project_type": "transit_corridor",
"parcels": [
{
"id": "P001",
"address": "100 Main Street",
"area_sqm": 2500,
"estimated_value": 750000,
"criticality": "critical",
"complexity": "high",
"holdout_risk": 0.6
}
],
"priorities": {
"criticality": 0.5,
"holdout_risk": 0.3,
"complexity": 0.2
},
"resources": {
"appraisers": 3,
"negotiators": 5,
"legal_staff": 2
},
"contingencies": {
"valuation_uncertainty": 0.10,
"negotiation_premium": 0.05,
"litigation_reserve": 0.15,
"inflation": 0.03
},
"delay_analysis": {
"interest_rate": 0.05,
"construction_cost_per_day": 50000,
"revenue_loss_per_day": 25000,
"project_start_delay_days": 90
}
}
See land_assembly_input_schema.json for complete schema documentation.
Sample Input
A 50-parcel transit corridor example is provided:
python land_assembly_calculator.py samples/sample_1_transit_corridor_50_parcels.json
Output
Markdown Report Sections
- Executive Summary - Key metrics table
- Acquisition Phasing Strategy - Phases, parallel tracks, top priority parcels
- Budget Analysis - Budget summary, contingency breakdown, budget by criticality
- Resource Allocation Plan - Timeline, costs, utilization
- Cost of Delay Analysis - Delay costs for critical parcels (if applicable)
JSON Output
Complete structured output including:
- Metadata (project name, timestamp, version)
- Phasing strategy (phases, parallel tracks, scored parcels)
- Budget analysis (base, contingencies, total, breakdown)
- Resource allocation (timeline, costs, utilization)
- Delay cost analysis (if applicable)
- Input parameters (for reproducibility)
Shared Utilities
This calculator uses the following shared modules:
land_assembly_utils.py
calculate_phasing_strategy()- Phasing algorithmmulti_parcel_budget()- Budget calculationcost_of_delay()- Delay cost analysisresource_allocation_plan()- Resource planningcontingency_budget()- Contingency calculation
timeline_utils.py
calculate_critical_path()- Critical path analysis (for timeline)calculate_resource_requirements()- Resource requirement calculation
risk_utils.py
assess_holdout_risk()- Holdout risk assessmentlitigation_risk_assessment()- Litigation probability
Best Practices
1. Parcel Criticality Classification
Critical Parcels:
- Block entire project alignment
- Required for project start
- No alternative alignment possible
- High priority for early acquisition
High Priority:
- Major impact on alignment or cost
- Limited alternatives available
- Significant project delay if not acquired
- Moderate priority for early acquisition
Medium Priority:
- Some flexibility in alignment
- Multiple alternatives available
- Moderate project impact
- Can be acquired in later phases
Low Priority:
- Minimal project impact
- Many alternatives available
- Optional or enhancement parcels
- Acquire last to preserve budget
2. Holdout Risk Assessment
High Risk (0.6 - 1.0):
- Owner emotionally attached to property
- Business-critical location
- Sophisticated owner with legal representation
- Limited relocation options
- Previous experience with holdouts
Medium Risk (0.3 - 0.6):
- Owner has moderate attachment
- Some business impact
- Some relocation options available
- Moderate negotiation experience
Low Risk (0.0 - 0.3):
- Owner willing to sell
- Financial need for liquidity
- Many relocation options
- Limited negotiation sophistication
- Timeline pressure to relocate
3. Complexity Assessment
High Complexity:
- Multiple owners or tenants
- Environmental contamination
- Title defects or encumbrances
- Zoning or land use issues
- Heritage designation
Medium Complexity:
- Single owner with some complications
- Minor environmental concerns
- Standard title review required
- Typical zoning compliance
Low Complexity:
- Single owner, clear title
- No environmental issues
- Standard zoning
- Cooperative owner
4. Resource Planning
Appraisers:
- 1 appraiser per 15-20 parcels (with 10 days/parcel)
- Increase if complex valuations or tight deadlines
- Consider hiring external appraisers for overflow
Negotiators:
- 1 negotiator per 10 parcels (with 30 days/parcel)
- Increase for high holdout risk parcels
- Senior negotiators for critical parcels
Legal Staff:
- 1 lawyer per 25 parcels (with 5 days/parcel)
- Increase if title issues or litigation expected
- External counsel for complex cases
5. Budget Contingencies
Adjust contingencies based on:
- Market conditions (hot market = higher premium)
- Owner sophistication (experienced = higher negotiation costs)
- Timeline pressure (tight schedule = higher costs)
- Litigation history (hostile jurisdiction = higher reserve)
- Inflation environment (high inflation = larger adjustment)
Key Terms
- Land Assembly - Acquisition of multiple adjacent or corridor parcels
- Critical Parcel - Parcel essential for project success
- Holdout Risk - Probability owner refuses reasonable offers
- Phasing Strategy - Sequential acquisition plan by priority
- Parallel Track - Multiple parcels acquired simultaneously
- Litigation Reserve - Budget contingency for expropriation proceedings
- Cost of Delay - Financial impact of delayed parcel acquisition
- Resource Allocation - Distribution of staff across parcels
- Priority Score - Weighted ranking for acquisition sequence
Related Skills
- expropriation-compensation-entitlement-analysis - Statutory compensation calculation
- injurious-affection-assessment - Construction and proximity damages
- agricultural-easement-negotiation-frameworks - Farm operation impacts
- easement-valuation-methods - ROW and easement valuation
- expropriation-statutory-deadline-tracking - Timeline management
Examples
Transit Corridor (50 Parcels)
Scenario: Urban LRT corridor requiring 50 parcels
- 8 critical parcels (station sites, alignment constraints)
- 15 high priority parcels (main corridor)
- 15 medium priority parcels (some flexibility)
- 12 low priority parcels (optional enhancements)
Strategy:
- Phase 1 (3 months): 8 critical parcels, parallel acquisition
- Phase 2 (4 months): 15 high priority parcels, parallel acquisition
- Phase 3 (5 months): 15 medium priority parcels, sequential
- Phase 4 (6 months): 12 low priority parcels, sequential
Budget: $40M base + $13M contingencies (32%) = $53M total
Highway Expansion (100 Parcels)
Scenario: Highway widening requiring 100 parcels
- 10 critical parcels (bridges, interchanges)
- 30 high priority parcels (main alignment)
- 40 medium priority parcels (some flexibility)
- 20 low priority parcels (noise walls, drainage)
Strategy:
- Phase 1: 10 critical, 5 parallel tracks
- Phase 2: 30 high priority, 6 parallel tracks
- Phase 3: 40 medium priority, sequential
- Phase 4: 20 low priority, sequential
Budget: $75M base + $24M contingencies (32%) = $99M total
Transmission Line (200 Parcels)
Scenario: 50km transmission corridor requiring 200 easements
- 25 critical parcels (tower sites, substation)
- 75 high priority parcels (main corridor)
- 75 medium priority parcels (some routing flexibility)
- 25 low priority parcels (access roads)
Strategy:
- Phase 1: 25 critical, 5 parallel tracks, 6 months
- Phase 2: 75 high priority, 10 parallel tracks, 9 months
- Phase 3: 75 medium priority, sequential, 12 months
- Phase 4: 25 low priority, sequential, 6 months
Budget: $15M base + $5M contingencies (33%) = $20M total
Version History
- 1.0.0 (2025-11-17) - Initial release with phasing, budgeting, resource allocation, and delay cost analysis
Author
Claude Code - Commercial Real Estate Lease Analysis Toolkit
Score
Total Score
Based on repository quality metrics
SKILL.mdファイルが含まれている
ライセンスが設定されている
100文字以上の説明がある
GitHub Stars 100以上
1ヶ月以内に更新
10回以上フォークされている
オープンIssueが50未満
プログラミング言語が設定されている
1つ以上のタグが設定されている
Reviews
Reviews coming soon