implementation-velocity-tracking
by onshoreoutsourcing
AI-powered desktop development environment with conversational file operations
SKILL.md
name: implementation-velocity-tracking description: Track and analyze implementation velocity metrics (actual vs estimated hours, defects per wave, test coverage trends, completion rates) to provide data-driven estimates for remaining work. Records wave completion metrics, calculates team velocity, identifies quality trends, predicts completion dates, and generates velocity dashboards. Use after wave completion, before epic planning, for sprint reviews, stakeholder reporting, or process improvement analysis.
Implementation Velocity Tracking
Tracks actual implementation velocity and provides predictive estimates for remaining work based on historical data.
Quick Start
Record wave completion metrics:
"Record metrics for wave-5.1.1: 28 actual hours, 24 estimated, 3 defects, 92% coverage"
Estimate remaining work:
"Estimate completion time for remaining waves in Feature 5 using historical velocity"
Analyze quality trends:
"Analyze defect density and test coverage trends for last 30 days"
Core Workflow
Step 1: Record Wave Completion Metrics
After each wave completes, record actual metrics:
Timing Metrics:
- Estimated hours (from wave plan)
- Actual hours worked
- Start date
- Completion date
- Duration (calendar days)
Quality Metrics:
- Defects found (during development)
- Defects found (post-release)
- Test coverage percentage
- Code review cycle time
- Rework percentage
Deliverables:
- User stories completed
- User stories deferred
- Acceptance criteria met
- Technical debt created
Step 2: Calculate Velocity Metrics
Wave Velocity:
Wave Velocity = Actual Hours / Estimated Hours
Examples:
- 1.0 = Perfect estimate
- 0.8 = Finished early (20% faster than estimated)
- 1.25 = Took longer (25% over estimate)
Rolling Average Velocity (last N waves):
Team Velocity = Average(Wave Velocities)
Velocity Trend:
- Improving: Velocity decreasing toward 1.0
- Stable: Velocity consistent
- Worsening: Velocity increasing (taking longer than estimated)
Step 3: Track Quality Metrics
Defect Density:
Defect Density = Defects Found / KLOC (thousands of lines of code)
Or simpler:
Defects per Wave = Average defects across waves
Test Coverage Trend:
- Track coverage percentage over time
- Identify waves with low coverage
- Set coverage targets (e.g., >90%)
Rework Percentage:
Rework % = (Rework Hours / Total Hours) × 100
Step 4: Generate Predictive Estimates
Estimate Remaining Work:
Adjusted Estimate = Base Estimate × Team Velocity
Example:
- Remaining waves: 5 waves
- Estimated hours: 120 hours total
- Team velocity: 1.12
- Adjusted estimate: 120 × 1.12 = 134 hours
Calendar Estimate (with team size):
Calendar Days = Adjusted Hours / (Team Size × Hours per Day)
Example:
- Adjusted hours: 134
- Team size: 2 developers
- Hours per day: 8
- Calendar days: 134 / (2 × 8) = 8.4 days
Confidence Level:
- High: Based on 15+ completed waves
- Medium: Based on 5-14 completed waves
- Low: Based on <5 completed waves
Step 5: Analyze Trends and Generate Reports
Create report in Docs/reports/velocity/metrics-{date}.md:
# Velocity and Quality Metrics Report
**Date**: YYYY-MM-DD
**Scope**: [Epic/Feature/All]
**Period**: Last 30 days
## Executive Summary
[1-2 sentences on team velocity and quality trends]
## Velocity Metrics
- Current Team Velocity: X.XX
- Trend: [Improving/Stable/Worsening]
- Completed Waves: X
- Average Hours per Wave: XX
## Quality Metrics
- Defect Density: X.X per wave
- Test Coverage: XX%
- Rework Percentage: XX%
## Predictive Estimates
- Remaining Waves: X
- Base Estimate: XX hours
- Adjusted Estimate: XX hours (with velocity)
- Expected Completion: YYYY-MM-DD
## Trend Analysis
[Charts and analysis of trends over time]
## Recommendations
[Actions to improve velocity or quality]
Use scripts/calculate_velocity.py and scripts/predict_completion.py.
Key Concepts
Velocity: Ratio of actual hours to estimated hours (1.0 = perfect estimate)
Team Velocity: Rolling average velocity across recent waves
Defect Density: Number of defects per wave or per KLOC
Test Coverage: Percentage of code covered by tests
Rework: Time spent fixing issues in already-completed code
Adjusted Estimate: Base estimate multiplied by team velocity
Confidence Level: Reliability of prediction based on historical data quantity
Velocity Trend: Direction velocity is moving (improving/stable/worsening)
Available Resources
Scripts
-
scripts/calculate_velocity.py — Calculates velocity metrics from wave data
python scripts/calculate_velocity.py \ --wave wave-5.1.1 \ --estimated 24 \ --actual 28 \ --output velocity-db.json # Output: Wave Velocity: 1.17, Team Velocity: 1.12 -
scripts/predict_completion.py — Predicts completion date using historical velocity
python scripts/predict_completion.py \ --remaining-waves 5 \ --estimated-hours 120 \ --velocity-db velocity-db.json \ --team-size 2 # Output: Expected Completion: 2025-02-05 (±2 days) -
scripts/analyze_trends.py — Analyzes quality and velocity trends
python scripts/analyze_trends.py \ --velocity-db velocity-db.json \ --metrics defect-density,coverage,velocity \ --period 30 # Output: Trend charts and analysis
References
- references/velocity-tracking-guide.md — Comprehensive guide to velocity tracking
- references/metrics-definitions.md — Definitions of all tracked metrics
- references/estimation-best-practices.md — How to improve estimation accuracy
Tracking Phases
Phase 1: Initial Calibration (First 3-5 Waves)
When: Starting new project or team Focus: Establish baseline velocity Output: Initial velocity estimate Note: Low confidence, wide variance expected
Phase 2: Velocity Stabilization (Waves 6-15)
When: Team finding rhythm Focus: Track velocity convergence Output: Medium confidence estimates Note: Velocity should stabilize around consistent value
Phase 3: Mature Velocity Tracking (Wave 15+)
When: Established team and process Focus: Fine-tuning and quality optimization Output: High confidence estimates Note: Focus shifts from velocity to quality metrics
Phase 4: Continuous Improvement
When: Ongoing Focus: Process optimization Output: Trend analysis and recommendations Note: Use data to drive process improvements
Common Velocity Patterns
Pattern 1: Early Optimism (First 3 waves)
Velocity starts low (0.6-0.8), then increases to 1.2-1.5
Cause: Initial estimates too optimistic
Solution: Calibrate estimates upward
Pattern 2: Learning Curve (Waves 1-10)
Velocity high initially (1.5+), gradually decreases to 1.0-1.1
Cause: Team learning codebase and process
Solution: Normal, velocity will stabilize
Pattern 3: Technical Debt Impact
Velocity gradually increasing (1.0 → 1.3 → 1.5)
Cause: Accumulated technical debt slowing development
Solution: Dedicate waves to refactoring
Pattern 4: Scope Creep
Velocity consistently high (1.3-1.5)
Cause: Scope creeping beyond estimates
Solution: Better scope control in wave planning
Pattern 5: Quality Issues
Velocity low (0.8-0.9) but defect density high
Cause: Rushing to meet deadlines, creating defects
Solution: Allow realistic timelines, improve quality
Output Format
Console Output:
Implementation Velocity Tracking
================================
Wave: 5.1.1 - Singleton Patterns
Completed: 2025-01-21
Velocity Metrics:
Estimated Hours: 24
Actual Hours: 28
Wave Velocity: 1.17 (17% over estimate)
Team Velocity (last 8 waves):
Average: 1.12
Trend: ↓ Improving (was 1.25)
Standard Deviation: 0.08
Quality Metrics:
Defects Found: 3
Defect Density: 2.8 per wave (↓ improving)
Test Coverage: 92% (↑ improving)
Rework: 2 hours (7%)
Updated Velocity Database: velocity-db.json
Predictive Estimate (remaining 5 waves):
Base Estimate: 120 hours
Adjusted (velocity 1.12): 134 hours
With 2-person team: 67 hours/person
Expected Completion: 2025-02-05 (±2 days)
Confidence: MEDIUM (8 completed waves)
Report: Docs/reports/velocity/wave-5.1.1-metrics-2025-01-21.md
Integration with Workflow
/implement-waves integration:
## Step 7: Record Velocity Metrics
After wave completion:
- Record actual hours worked
- Record defects found
- Record test coverage achieved
- Invoke `implementation-velocity-tracking` skill
- Update velocity database
- Review velocity trends
/design-waves integration:
## Step 0.5: Adjust Estimates Using Velocity
Before estimating new waves:
- Check current team velocity
- Adjust estimates by velocity factor
- Use historical data for similar wave types
- Account for team size changes
/review-waves integration:
## Wave Retrospective: Velocity Review
During wave retrospective:
- Review velocity for completed wave
- Compare to team average
- Identify causes of variance
- Document lessons learned
- Adjust future estimates
Epic Planning:
## Epic Estimation
Before committing to epic:
- Estimate total hours for all features
- Multiply by team velocity
- Add buffer for uncertainty
- Calculate expected duration
- Get stakeholder buy-in on timeline
Success Criteria
- ✅ All completed waves have recorded metrics
- ✅ Velocity calculated accurately
- ✅ Quality metrics tracked consistently
- ✅ Trends analyzed and visualized
- ✅ Predictive estimates generated
- ✅ Confidence level appropriate
- ✅ Report generated in standard format
- ✅ Recommendations provided for improvement
Tips for Accurate Velocity Tracking
- Record immediately - Record metrics right after wave completion
- Be honest - Accurate data is more valuable than optimistic data
- Track consistently - Use same metrics for all waves
- Sufficient history - Need 5+ waves for reliable predictions
- Adjust for context - Account for team changes, complexity variations
- Review trends - Look for patterns, not individual waves
- Use for learning - Velocity is a tool for improvement, not judgment
Examples
Example 1: Record Wave Completion
Command:
"Record velocity metrics for wave-5.1.1: 28 actual hours, 24 estimated, 3 defects, 92% coverage"
Process:
- Read velocity database (velocity-db.json)
- Calculate wave velocity: 28 / 24 = 1.17
- Update rolling average: (previous avg + 1.17) / n
- Record quality metrics
- Save to database
Output:
- Wave Velocity: 1.17 (17% over)
- Team Velocity: 1.12 (updated average)
- Defect Density: 2.8 per wave (improving)
- Test Coverage: 92% (on target)
Example 2: Predict Remaining Work
Command:
"Estimate completion for remaining Feature 5 waves using historical velocity"
Process:
- Read velocity database
- Get team velocity: 1.12
- Find remaining waves: 5 waves
- Sum estimated hours: 120 hours
- Apply velocity: 120 × 1.12 = 134 hours
- Calculate calendar: 134 / (2 × 8) = 8.4 days
- Add confidence interval: ±2 days
Output:
- Adjusted Estimate: 134 hours
- Expected Completion: 2025-02-05
- Confidence: MEDIUM (8 waves of history)
Example 3: Analyze Quality Trends
Command:
"Analyze defect density and test coverage trends for last 30 days"
Process:
- Read velocity database
- Filter waves from last 30 days
- Calculate defect density trend
- Calculate test coverage trend
- Identify anomalies
- Generate recommendations
Output:
Quality Trends (Last 30 Days):
Defect Density:
Trend: 📈 IMPROVING (4.2 → 2.8 per wave)
Target: <3.0 ✅ ACHIEVED
Test Coverage:
Trend: 📈 IMPROVING (85% → 92%)
Target: >90% ✅ ACHIEVED
Alert: Defect spike in wave-5.3.1 (7 defects)
Recommendation: Investigate root cause
Last Updated: 2025-01-21
スコア
総合スコア
リポジトリの品質指標に基づく評価
SKILL.mdファイルが含まれている
ライセンスが設定されている
100文字以上の説明がある
GitHub Stars 100以上
3ヶ月以内に更新がある
10回以上フォークされている
オープンIssueが50未満
プログラミング言語が設定されている
1つ以上のタグが設定されている
レビュー
レビュー機能は近日公開予定です